Project Update

Our next meeting will be held on Monday, July 10, 2017, at the old high school at 5:00 PM. Agenda items will be included in a future update.

NMRHS will be moving from the old high school to the new building starting Wednesday, June 28th through July 7th. There will be a major transition in a week and a half time frame. During this period if you are unable to reach staff by phone at the high school, please use email to facilitate the process.

View updated photos along with a layout detailing the five “Areas” of the building.

Project Update

Our next meeting will be held on Monday, June 12, 2017, at the high school at 5:00 PM. Agenda items include the following:

OPM REPORT:

  1. Construction Progress Photo Update.
  2. Review Construction Project Schedule
  3. Review Project Budget
  4. Review/Approve Contractors Construction Change Order
    1. Construction Change Order Summary
  5. Update on Western Ballfields – Grading/Sod Changes
  6. Review/Approve Technology-TV Studio & Computers Bid Results – to be presented

NEW BUSINESS:

  1. General Discussion
  2. Common Area – Large Format Tile Installation – Subcontractor Performance
  3. Update of Gym Volleyball Court Nets
  4. Other Business Not Reasonably Anticipated within 48 hours of Meeting
  5. 2017/18 Building Committee Schedule

View updated photos along with a layout detailing the five “Areas” of the building.

Project Update

Our next meeting will be held on Monday, June 12, 2017, at the high school at 5:00 PM. Agenda items will be included in a future update.

Work ongoing the week of 5/29:

  • Complete finish paint in A-1
  • Priming and painting walls in the auditorium
  • Continue working on tasks to complete items in A building and B-1
  • Continue back punching in A/ B /D buildings
  • Clean B-1 and administration building- send out updated work to complete list to SMMA
  • Continue interior masonry in vestibule in the Commons
  • Complete exterior storefront trim
  • Install MEP finishes in toilet /shower rooms in E building
  • Install millwork in A / C building
  • Continue floor tile in kitchen server-Commons area
  • Complete tile in stair # 1 and re-work stair # 2
  • Install acoustical wall panels in B building
  • Continue balancing in B and start process in A building
  • Complete MEP insulation in all areas
  • Continue nailing and start sanding gym flooring
  • Continue taping and sanding touch up throughout building
  • Install rubber stair # 2 /rubber in PE room
  • Close up ceilings in the corridors in C and E buildings
  • Continue exterior site work/rebar and forming and placing concrete sidewalks-west and south elevations
  • Continue site plantings
  • Install miscellaneous railings in stairways and auditorium

View updated photos along with a layout detailing the five “Areas” of the building.

Project Update

Our next meeting will be held on Monday, June 12, 2017, at the high school at 5:00 PM. Agenda items will be included in a future update.

Work ongoing the week of 5/22:

  • Complete finish paint in A-1
  • Priming and painting walls in auditorium
  • Back punching of A/ B /D buildings
  • Continue interior masonry in the vestibule in Commons /clean up east elevation
  • Complete exterior storefront trim
  • Install linoleum in C-2 / install rubber in stairways
  • Install millwork in A / C buildings
  • Start grinding floor and layout for floor tiling in Commons
  • Start floor tile in kitchen servery
  • Complete tile in stair # 1 and re-work in stair # 2
  • Install acoustical wall panels in B building
  • Continue balancing in B building and start in A building
  • Complete MEP insulation in all areas
  • Continue nailing and start sanding gym flooring
  • Continue taping and sanding touch up throughout the building
  • Close up ceilings in the corridors in C and E buildings
  • Continue exterior site work/rebar/forming and placing concrete sidewalks in west and south elevations
  • Install curbing in north elevation
  • Continue site plantings
  • Complete epoxy walls and floors in locker rooms
  • Install finishes in lockers rooms
  • Install miscellaneous railings in stairways and auditorium

View updated photos along with a layout detailing the five “Areas” of the building.

Project Update

Our next meeting will be held on Monday, May 15, 2017, at the high school at 5:00 PM. Agenda items will include the following:

  • Construction progress photo update
  • Review construction project schedule
  • Review project budget
  • Review and discuss gym logo
  • Review of change orders
  • Review/approve technology-AV & projectors bid results – to be presented
  • Review/approve OPM contract amendment

New Business:

  1. General Discussion
  2. Authorization for Superintendent to Award Bid Packages Within Budget
    • TV Studio – Technology
    • Computers/Peripherals – Technology
    • Moving Services

Work ongoing the week of 5/15:

  • Complete trim on exterior storefronts in east elevation
  • Complete exterior masonry in east elevation and continue interior masonry at C vestibule
  • Complete finish paint in A-1
  • Complete corridor linoleum in A-1 and B-1 up to elevator front
  • Complete carpet tile in C building
  • Installing millwork in auditorium
  • Complete OH work list for C and E corridors and inspections
  • Continue set up of kitchen equipment
  • Continue tile in stair # 1 and re-work stair # 2
  • Rough MEP in auditorium and commons area
  • Insulate MEP piping in A, C and E buildings
  • Complete metal work on roof
  • Continue installation of gym flooring
  • Continue to touch up taping and sanding throughout the building
  • Continue exterior site work/rebar and forming and placing concrete sidewalks
  • Grading and tilling of softball field / continue irrigation piping
  • Installing ceiling at exterior loading dock
  • Continue cleaning of classrooms
  • Start epoxy walls and floors in locker rooms
  • Start installation of exterior plantings-weather permitting

View updated photos along with a layout detailing the five “Areas” of the building.

Project Update

Our next meeting will be held on Monday, May 15, 2017, at the high school at 5:00 PM. Agenda items will be included in a future update.

Work ongoing the week of May 8:

  • Complete trim on exterior storefronts in east elevation
  • Complete exterior masonry in east elevation and continue interior masonry at C vestibule
  • Continue finish paint in A-1
  • Complete corridor linoleum in B-1 up to elevator front
  • Prep for linoleum in A-1
  • Install carpet tile in C building
  • Install millwork in auditorium
  • Complete ceiling grid in C corridors 1st floor
  • Continue setting up kitchen equipment
  • Complete porcelain tile in A building and start installation in stairway #1
  • Close up ceiling in C-2 and A-1 corridor
  • Continue MEP finishes in B / A and E buildings / Complete D and B building balancing
  • Continue with hook up of equipment in kitchen area
  • Rough MEP in auditorium and commons areas
  • Install MEP piping in A/C/E buildings and mechanical space
  • Complete toilet partition installation with accessories
  • Continue the metal work on the roof
  • Continue installation of gym floor
  • Continue taping and sanding in C building
  • Continue exterior site work/rebar and forming and placing concrete sidewalks
  • Install binder in north and west elevations
  • Grading and tilling softball field / continue irrigation piping
  • Installation of ceiling at exterior loading dock
  • Continue cleaning of classrooms
  • Start epoxy walls and floors in locker rooms

View updated photos along with a layout detailing the five “Areas” of the building.

Project Update

Our next meeting will be held on Monday, May 15, 2017, at the high school at 5:00 PM. Agenda items will be included in a future update.

Work ongoing the week of May 1:

  • Complete trim on exterior storefronts in east elevation
  • Complete exterior masonry in east elevation and continue interior masonry at C vestibule
  • Continue finish paint in A-1
  • Complete corridor linoleum in B-1 up to elevator front
  • Prep for linoleum in A-1
  • Install carpet tile in C building
  • Install millwork in auditorium / C building
  • Complete ceiling grid in C corridors 1st floor
  • Continue setting up kitchen equipment
  • Complete porcelain tile in A building and start Stair # 1
  • Close up ceiling in C-2 corridor /A-1
  • Continue MEP finishes in B / A and E buildings / Complete D and start B building balancing
  • Continue with hook up of equipment in kitchen area
  • Rough MEP in A building/ auditorium / C commons area/ mechanical room space
  • Insulate MEP piping in A building / C building / E building and mechanical space
  • Continue metal work on roof
  • Continue installing gym flooring
  • Continue taping and sanding in C building
  • Continue exterior site work/rebar, forming and placing concrete sidewalks
  • Install binder in north and west elevations
  • Grading and tilling softball field / continue irrigation piping
  • Install ceiling at exterior loading dock
  • Continue cleaning of classrooms
  • Start epoxy walls and floors in locker rooms

View updated photos along with a layout detailing the five “Areas” of the building.

Project Update

Our next meeting will be held on Monday, May 15, 2017, at the high school at 5:00 PM. Agenda items will be included in a future update.

Work ongoing the week of May 1:

  • Continue installing trim on exterior storefronts east elevation
  • Continue exterior masonry east elevation and interior masonry at C vestibule
  • Complete finish paint in A/2-B/1
  • Complete corridor linoleum in B/2 up to elevator front
  • Prep and start install of linoleum in B/1
  • Install carpet tile in C building
  • Install millwork in auditorium
  • Install ceiling grid in C corridors 1st floor, complete grid in E building corridors
  • Continue ceiling grid in kitchen and server area
  • Continue setting up kitchen equipment
  • Continue porcelain tile in A building and stairway #1
  • Close up ceiling in C/2 corridor
  • Continue MEP finishes in A/B and E buildings

View updated photos along with a layout detailing the five “Areas” of the building.

Project Update

Our next meeting will be held on Monday, April 10, 2017, at the high school at 5:00 PM. Agenda items include the following:

  • OPM Report
    1. Construction Progress Update
    2. Review Construction Project Schedule
    3. Review Project Budget
    4. Review and discuss Contractors Construction Change Orders
    5. Review and discuss Designers Contract Amendments
    6. Review and discuss OPM Contract Amendments
  • New Business
    1. General Discussion
    2. Other Business Not Reasonably Anticipated within 48 hours of Meeting

The turf field presentation from the March 23rd public forum is now available. View now »

Work ongoing the week of April 10:

  • Complete porcelain clips in south elevation
  • Installing exterior trim in east elevation
  • Complete finish paint in D building / installing base in D building
  • Complete prep and start finish paint in B/2
  • Working on tasks to complete classrooms in B building
  • Complete porcelain wall tile in stair # 2, start stair # 1
  • MEP rough in auditorium / mechanical space in C building
  • Install toilet accessories in student and staff bathrooms
  • Install VCT /rubber in band and chorus rooms
  • Complete MEP in locker rooms/ close and tape ceilings
  • Complete hanging clouds in vestibule / complete soffit and hang clouds in weight room
  • Complete ceiling grid in kitchen and server area
  • Place kitchen equipment and start connections
  • Complete ceiling tiles in B building on both floors
  • Complete OH work to complete list in A building / electrical inspections
  • Insulating MEP in all areas
  • Installing MEP finishes in B/ A and C buildings
  • Continue to install millwork clouds in auditorium / C building
  • Continue interior masonry /exterior masonry
  • Continue interior and exterior caulking
  • Exterior site work in north and west elevation
  • Install carpet tile in B and D buildings
  • Installing ceiling grid in weight room/corridors in E building
  • Startup balance of RTUs

View updated photos along with a layout detailing the five “Areas” of the building.

Project Update

Our next meeting will be held on Monday, April 10, 2017, at the high school at 5:00 PM. Agenda items will be included in a future update.

Work ongoing the week of April 3:

  • Complete vestibule ceiling and porcelain clips in south elevation
  • Complete interior storefronts /continue glazing and hardware
  • Complete finish paint in D building / installing base in D building
  • Working on tasks to complete classrooms in B building
  • Complete porcelain wall tile in corridors B-1 and D-1
  • MEP rough in auditorium / mechanical space in C building
  • Install balance of lockers in B and C building / unload and start installing toilet accessories in D-1
  • Complete linoleum corridors in D building 1st floor- prep and start B-2 corridor for linoleum
  • Install MEP in locker rooms
  • Continue hanging clouds /drywall tape in Commons
  • Installing FRP walls in kitchen area
  • Start installing ceilings in kitchen and server area
  • Place kitchen equipment and start connections
  • Prep walls and start finish paint in B-2
  • Install ceiling tiles in B building/ both floors
  • Continue ceiling grid in C building media center / C building corridor
  • Insulation of MEP in all areas
  • Installing MEP finishes in B and A buildings – install acid pump in mechanical area
  • Continue to install millwork clouds in auditorium / C building
  • Continue interior masonry /exterior masonry
  • Continue interior and exterior caulking
  • Exterior site work north and west elevation
  • Complete OH work to complete list in A-1
  • Complete flooring at yoga room and start rough flooring gym
  • Install carpet tile in D building and B building
  • Complete ceiling and lights in media center
  • Start air balancing in D building
  • Factory startup of water heaters
  • Startup balance of RTUs

View updated photos along with a layout detailing the five “Areas” of the building.